Lakeside Company estimated manufacturing overhead costs for 2009 at $378,000, based on 180,000 estimated direct labor hours. Actual direct labor hours for 2009 totaled 195,000. Manufacturing overhead contains debit entries totaling $391,500. What was the amount of manufacturing overhead for 2009?
A) $31,500 underallocated
B) $31,500 overallocated
C) $18,000 underallocated
D) $18,000 overallocated
Answer: D
If the answers is incorrect or not given, you can answer the above question in the comment box. If the answers is incorrect or not given, you can answer the above question in the comment box.