Lakeside Company estimated manufacturing overhead costs for 2009 at $378,000, based on 180,000 estimated direct labor hours. Actual direct labor hours for 2009 totaled 195,000. Manufacturing overhead contains debit entries totaling $391,500. What was the amount of manufacturing overhead for 2009?

Lakeside Company estimated manufacturing overhead costs for 2009 at $378,000, based on 180,000 estimated direct labor hours. Actual direct labor hours for 2009 totaled 195,000. Manufacturing overhead contains debit entries totaling $391,500. What was the amount of manufacturing overhead for 2009?



A) $31,500 underallocated
B) $31,500 overallocated
C) $18,000 underallocated
D) $18,000 overallocated



Answer: D